How to Calculate Concrete Footings
Trench length times width times depth, all three in feet, then divide by 27. A 56 ft trench 16 inches wide and 8 inches deep works out to 49.8 cubic feet, which is 1.84 cubic yards. Add 10% for over-dig and a trench wall that caved a little, and you’re ordering 2.5 cubic yards.
The concrete footing calculator above does that on every keystroke, for all three things people call a footing: a continuous run under a wall, a square pad under a post, and a round pier. All three are tabs on the same form, and the Assumptions box under the results tells you straight out when the size you typed is under the code minimum.
- Pick the tab: Continuous for a trench under a wall, Square pad for a post, Round pier for a tube or an augered hole.
- Enter the length in feet and the width and thickness in inches, the way the plan note reads them.
- Use "Add another footing" for the pads or piers in the same pour, so one order covers the job.
- Leave the waste chip at 10% unless the trench is clean and square, then read the half-yard order off the card.
Cubic yards = length(ft) × width(in) ÷ 12 × depth(in) ÷ 12 ÷ 27
Continuous footing: 16 in × 8 in is 0.889 cu ft per linear foot
Square pad: side(in) ÷ 12 × side(in) ÷ 12 × thickness(in) ÷ 12
Round pier: 3.1416 × (diameter(in) ÷ 24)² × depth(in) ÷ 12
Bags: 45 × 80 lb or 60 × 60 lb per cubic yard
Worked example · 12 x 16 ft shed stem wall
Perimeter = 56 linear ft
56 × 16 in × 8 in = 49.8 cu ft
÷ 27, plus 10% = 2.03 cu yd
Order in half yards = 2.5 cu yd
Or bags = 92 × 80 lb
Form board = 112 linear ft
How to Measure Concrete for Footings
Measure the trench, not the wall. The footing is wider than the wall sitting on it, so the length that matches what the truck pours is a tape run along the trench. On a four-sided foundation take the centerline all the way round, not the outside edge, and feed that into the concrete footing calculator above.
Depth is what goes wrong, and it goes wrong by inches. To calculate concrete for footings you only need three measurements, but a machine-dug trench is never even and concrete finds every low spot. Set a line at the top of the pour and measure down in several places: what you need is the average depth, not the depth at one corner.
- Run a tape along the centerline of the trench, all the way round on a four-sided foundation.
- Measure the trench width at a few points and use the widest.
- Stretch a line at the top of the pour and measure down to the bottom in several places.
- Average those depths and enter length, width and average depth in the calculator above.
Here is what two inches costs. That 56 ft trench at 16 by 8 inches is 1.84 cubic yards. Dug to 10 inches it is 2.30 cubic yards, so 0.46 of a yard you pay for and never see. Most of the waste chip is gone before you spill a drop, which is why NRMCA CIP 31: Ordering Ready Mixed Concrete says to order 4% to 10% over the plan.
Concrete Footing Size and Depth: What the Code Sets
Footing width isn’t a preference. It comes from the weight above and the strength of the soil below, and the 2021 IRC prints the answer as a table. You can’t calculate footing size off a load without doing engineering, so read it off the table instead. Two numbers sit under all of it: not less than 12 inches wide and not less than 6 inches thick (R403.1.1).
| Wall above | Stories | 1,500 psf | 2,000 psf | 3,000 psf |
|---|---|---|---|---|
| Conventional light-frame construction | 1 | 12 in | 12 in | 12 in |
| Conventional light-frame construction | 2 | 15 in | 12 in | 12 in |
| Conventional light-frame construction | 3 | 23 in | 17 in | 12 in |
| 4 in brick veneer over light frame, or 8 in hollow concrete masonry | 1 | 12 in | 12 in | 12 in |
| 4 in brick veneer over light frame, or 8 in hollow concrete masonry | 2 | 21 in | 16 in | 12 in |
| 4 in brick veneer over light frame, or 8 in hollow concrete masonry | 3 | 32 in | 24 in | 16 in |
| 8 in solid concrete or masonry, or fully grouted masonry | 1 | 16 in | 12 in | 12 in |
| 8 in solid concrete or masonry, or fully grouted masonry | 2 | 29 in | 21 in | 14 in |
| 8 in solid concrete or masonry, or fully grouted masonry | 3 | 42 in | 32 in | 21 in |
Table R403.1, 2021 IRC, as printed in 2023 Oregon Residential Specialty Code, Chapter 4 (2021 IRC text, published by ICC), checked November 2026. Its 1,000 psf column runs from 18 in up to 63 in. Local amendments change these numbers.
With no soils report, the code lets you assume a bearing value off its own list:
| Soil under the footing | Bearing |
|---|---|
| Crystalline bedrock | 12,000 psf |
| Sedimentary and foliated rock | 4,000 psf |
| Sandy gravel and/or gravel (GW, GP) | 3,000 psf |
| Sand, silty sand, clayey sand, silty gravel and clayey gravel (SW, SP, SM, SC, GM, GC) | 2,000 psf |
| Clay, sandy clay, silty clay, clayey silt, silt and sandy silt (CL, ML, MH, CH) | 1,500 psf |
Table R401.4.1, 2021 IRC, as printed in 2023 Oregon Residential Specialty Code, Chapter 4 (2021 IRC text, published by ICC), checked November 2026. Where the official expects less than 1,500 psf on site, a soils investigation sets the value instead.
Plain clay and silt are the bottom row, so the 1,500 psf column is the safe one to read for most residential work. A footings and foundations calculator can’t pick your row, because the row depends on what goes up on top. A building official can pick it in a minute.
Depth and thickness get mixed up constantly. Thickness is how much concrete you pour, which is the figure the concrete footing calculator wants. Depth is how far down the bottom sits: at least 12 inches below finished grade on undisturbed ground, and below the frost line if that’s deeper (R403.1.4). The code names a local table for frost depth, so only your building department has that number.
One rule catches almost everybody. The footing projects past the wall, and that projection may be no less than 2 inches and no more than the footing is thick. An 8 inch stem wall on a 24 inch footing projects 8 inches each side, so that footing has to be 8 inches thick, not the 6 inch minimum. Wide and thin isn’t a legal footing.
Concrete for Footings by Size
Screenshot this one before you drive to the yard. Every row is per linear foot, so multiply by your trench length, or type the trench into the concrete footing calculator.
| Footing (W x D) | Cu ft per ft | Cu yd per 10 ft | Cu yd per 50 ft | 80 lb bags per 10 ft |
|---|---|---|---|---|
| 12 x 6 in | 0.5 | 0.19 | 0.93 | 9 |
| 16 x 8 in | 0.9 | 0.33 | 1.65 | 15 |
| 16 x 10 in | 1.1 | 0.41 | 2.06 | 19 |
| 20 x 8 in | 1.1 | 0.41 | 2.06 | 19 |
| 20 x 10 in | 1.4 | 0.51 | 2.57 | 24 |
| 24 x 10 in | 1.7 | 0.62 | 3.09 | 28 |
| 24 x 12 in | 2.0 | 0.74 | 3.70 | 34 |
Volumes from the formula above. Bag counts at 45 bags of 80 lb per cubic yard, per Quikrete Concrete Mix 1101 data sheet. Add 10% before you order.
The 16 by 8 row against the 24 by 12 row is why size matters to your wallet: same trench length, 125% more concrete. Figuring concrete footings at the wrong size costs money both ways.
How to Calculate Cement for Footings
Cement is one ingredient. Concrete is cement plus sand, gravel and water, and concrete is what goes in a footing. Ask the yard for “cement” for a footing and you may get the wrong pallet: portland cement isn’t concrete mix and won’t set up into a footing on its own.
Bagged mix is sold by what it yields. One 80 lb bag makes 0.60 cubic feet, so a cubic yard takes 45. The 56 ft shed footing is 92 bags of 80 lb or 122 of 60 lb, which is 4.11 tons to move by hand. That’s where a truck stops being a luxury.
- Work out the footing volume in cubic feet with the calculator above.
- Divide by the yield on the bag: 0.60 cubic feet for an 80 lb bag of concrete mix, not plain cement.
- Round up to whole bags, then add the waste chip.
- Compare the total against a ready-mix price before you load the cart.
Footing concrete is ordinary mix: nothing goes into a footing that doesn’t go into a slab, so a bag marked for general use is the bag you want.
Pads and piers go the other way. Six 24 inch pads 10 inches thick come to 0.81 cubic yards, or 37 bags, and one 12 inch pier 36 inches deep is only 0.10 cubic yards, so a wheelbarrow beats a short load fee. A pier concrete calculator and a pad calculator are the same arithmetic with a different cross-section, which is why they’re two tabs and not two pages. The concrete bag calculator prices bags by the pallet.
Deck Footing Calculator: Pier Sizes From the Span Table
A deck footing is sized a different way, and it’s where a lot of DIY deck plans go wrong. You don’t work out a load. You read the footing off the beam span and the joist span, two numbers already on your plan, from Table 4 of AWC DCA 6: Prescriptive Residential Wood Deck Construction Guide.
| Beam span | Joist span | Round | Square | Thick | Cu yd per pier |
|---|---|---|---|---|---|
| 6 ft | 10 ft | 18 in | 16 x 16 in | 7 in | 0.07 |
| 6 ft | 14 ft | 21 in | 18 x 18 in | 8 in | 0.09 |
| 6 ft | 18 ft | 24 in | 21 x 21 in | 10 in | 0.12 |
| 8 ft | 10 ft | 20 in | 18 x 18 in | 8 in | 0.08 |
| 8 ft | 14 ft | 24 in | 21 x 21 in | 10 in | 0.12 |
| 8 ft | 18 ft | 27 in | 24 x 24 in | 11 in | 0.15 |
| 10 ft | 10 ft | 23 in | 20 x 20 in | 9 in | 0.11 |
| 10 ft | 14 ft | 27 in | 24 x 24 in | 11 in | 0.15 |
| 10 ft | 18 ft | 31 in | 27 x 27 in | 13 in | 0.19 |
| 12 ft | 10 ft | 25 in | 22 x 22 in | 10 in | 0.13 |
| 12 ft | 14 ft | 30 in | 26 x 26 in | 13 in | 0.18 |
| 12 ft | 18 ft | 34 in | 30 x 30 in | 15 in | 0.23 |
| 14 ft | 10 ft | 27 in | 24 x 24 in | 11 in | 0.15 |
| 14 ft | 14 ft | 32 in | 29 x 29 in | 14 in | 0.21 |
| 14 ft | 18 ft | 37 in | 33 x 33 in | 16 in | 0.28 |
| 16 ft | 10 ft | 29 in | 26 x 26 in | 12 in | 0.17 |
| 16 ft | 14 ft | 35 in | 31 x 31 in | 15 in | 0.25 |
| 16 ft | 18 ft | 40 in | 35 x 35 in | 18 in | 0.32 |
| 18 ft | 10 ft | 31 in | 27 x 27 in | 13 in | 0.19 |
| 18 ft | 14 ft | 37 in | 33 x 33 in | 16 in | 0.28 |
| 18 ft | 18 ft | 42 in | 37 x 37 in | 19 in | 0.36 |
AWC DCA 6: Prescriptive Residential Wood Deck Construction Guide, Table 4, AWC DCA 6, based on the 2015 IRC, checked November 2026. Assumes 1,500 psf soil, 150 pcf concrete, 2,500 psi mix, 40 psf live and 10 psf dead load. The last column is concrete per pier at the 12 in minimum depth; a deeper frost line takes proportionally more.
Take the row your spans land on, or the next row up if you fall between two. Beams spanning 6 ft with joists spanning 14 ft want a 21 inch round pier, or a square pad 18 inches on a side, 8 inches thick. Four of those 48 inches deep is 1.57 cubic yards. Two spans in, one footing size out: that’s all it takes to calculate deck footings from the table.
Three things about that table nobody mentions:
- Deck footing spacing is the beam span, and it’s your call. Posts closer together mean smaller footings and more holes. Further apart means fewer, bigger holes. Both are in the table, so pick the one your auger prefers.
- A corner post carries less, and the table says so. A corner footing may be 0.9 of the size listed, per footnote 2 on Table 4.
- Within 5 feet of the house, the footing has to bear at the same elevation as the house foundation footing. That’s the most common re-dig on a ledger deck.
The table stops at 18 ft by 18 ft. Past that, or under a hot tub or a roof, it’s an engineer’s problem. Above the piers the deck board calculator counts boards, and the post hole concrete calculator is for a hole with a post set in it rather than a footing a post sits on.
Concrete Footing Cost Calculator: What a Footing Costs
The concrete itself we can price. Ready-mix runs $119 to $147 per cubic yard, national average, materials only, per HomeGuide: Concrete prices, verified November 2026. Under 10 cubic yards there’s also a short load surcharge of about $53 per cubic yard, and almost every footing job is a short load.
| Footing job | Cubic yards | Order | Ready-mix | Short load fee |
|---|---|---|---|---|
| Shed stem wall, 12 x 16 ft, 16 x 8 in | 2.03 | 2.5 cu yd | $298 to $368 | $133 |
| Garage stem wall, 24 x 24 ft, 20 x 10 in | 5.43 | 5.5 cu yd | $655 to $809 | $292 |
| Six 24 in pads under a carport | 0.81 | 1.0 cu yd | $119 to $147 | $53 |
| Four 21 in deck piers, 48 in deep | 1.57 | 2.0 cu yd | $238 to $294 | $106 |
Volumes include 10% waste. Prices from HomeGuide: Concrete prices, verified November 2026, plus the $53 per cubic yard short load surcharge. Materials only: no excavation, forms, steel or labor.
What we won’t print is a national price per linear foot. The cost guides we checked disagreed with each other by a factor of ten on the same footing, and no wonder: a footing price is excavation, forms, steel, concrete and a pump if the truck can’t reach, and those vary more by site than by state.
Take the yardage off the concrete footing calculator, add the form board figure and call two foundation contractors with both. For the stone under the footing the gravel calculator sizes the base, and the cubic yard calculator converts a volume into what a plant sells.
Pouring a Footing and a Slab Together
A monolithic pour puts the footing and the slab in one placement. The slab edge thickens down into a footing, there’s no cold joint, and you pay one mobilization instead of two. Total both to see whether a truck makes sense. A 12 by 16 ft slab at 4 inches plus the 56 ft perimeter footing is 4.64 cubic yards, well past bags and comfortably inside one truck.
The concrete calculator has tabs for both, and the concrete slab calculator does the slab alone if the footing is already in.
Whether your code allows it comes back to frost depth. A thickened edge reaches a 12 inch frost line. Four feet down it does not, and you’re pouring a footing and a stem wall separately, which the concrete block calculator counts the block for.
Concrete Footing Estimator Tips Before You Pour
A concrete footing estimator gets you a number. These decide whether it survives the morning of the pour.
- Re-measure the trench before the truck is booked. Width, depth and length, three places each, then retype them into the concrete footing calculator. Everything after that’s multiplication, so an inch of trench error is an inch of error on the invoice.
- Pour against undisturbed soil, not backfill. Over-dig gets concrete, or engineered fill you compact and have inspected. Never loose dirt.
- Keep the top level. A sloping lot gets stepped footings, not a wedge.
- Steel in and tied before the truck arrives. Rebar pushed into placed concrete does nothing. The rebar calculator counts bars once your building department has given you the spacing.
- Book the inspection, then order in half yards. The official checks bearing conditions before concrete goes in, and plants sell half yards, so 2.03 yards is a 2.5 yard order.
this page gives you volume, bags, cost and the published size tables. The footing size your project needs, its depth below the frost line, the reinforcing in it and whether the soil under it carries what the tables assume are all decisions for your building department or an engineer. Get them before you dig, not after you pour.
Concrete Footing Calculator FAQ
How do you work out concrete for footings?
Length times width times depth, in feet, divided by 27. A 56 ft trench 16 inches wide and 8 inches deep is 49.8 cubic feet, so 1.84 cubic yards, or 2.03 once you add 10% for over-dig. That is 92 bags of 80 lb mix, or a 2.5 cubic yard ready-mix order.
How do I calculate concrete for a deck footing?
Get the footing size from the span table first, then treat it as a cylinder or a box. Four 21 inch round piers 48 inches deep take 1.57 cubic yards, which is 71 bags of 80 lb mix. One 12 inch pier 36 inches deep is only 0.10 cubic yards, so bags beat a truck on a small deck.
How many bags of concrete do I need for a footing?
A cubic yard takes 45 bags of 80 lb mix, 60 of 60 lb or 90 of 40 lb, because an 80 lb bag yields 0.60 cubic feet. The 56 ft footing above needs 92 bags of 80 lb mix. Past about 30 bags, call a plant.
How wide and how deep does a concrete footing have to be?
The 2021 IRC floor is 12 inches wide by 6 inches thick, and no footing may be smaller than that. The width you actually need comes from Table R403.1, which reads off your story count and your soil, and it runs from 12 inches up to 63 for a three story masonry wall on weak clay.
How deep do footings need to go below the frost line?
Exterior footings bear at least 12 inches below finished grade on undisturbed ground, and below the frost line if that's deeper. The code points at a local table for the frost depth rather than naming a number, so your building department is the only place to get it. Footings may not bear on frozen soil.
Is a concrete pier the same thing as a footing?
A pier is one kind of footing. A continuous footing runs under a wall and spreads its load along a trench, a pad sits under a single post or column, and a pier is a round version of a pad, usually a tube or an augered hole. All three do the same job, which is handing the load to soil that can carry it.
Do I need rebar in a concrete footing?
Often yes, and the size and spacing are a code question, not a math question. Seismic Design Categories D0, D1 and D2 have their own reinforcing rules, and local amendments are everywhere. Get the bar size and spacing from your building department or your engineer, then count the bars with the rebar calculator.
Should I pour the footing and the slab at the same time?
A monolithic pour puts the footing and the slab in one placement, which saves a mobilization and a cold joint. A 12 by 16 ft slab at 4 inches with a 56 ft perimeter footing comes to 4.64 cubic yards together, enough that a truck makes sense. Whether your code allows it depends on your frost depth.
Related Calculators
Sources
- 2023 Oregon Residential Specialty Code, Chapter 4 (2021 IRC text, published by ICC),
- AWC DCA 6: Prescriptive Residential Wood Deck Construction Guide, Table 4,
- HomeGuide: Concrete prices,
- Lowe's: Quikrete and Sakrete 80 lb concrete mix,
- Quikrete Concrete Mix 1101 data sheet,
- Engineering ToolBox: Concrete properties,
- NRMCA CIP 31: Ordering Ready Mixed Concrete,
Assumptions
What this calculator used for the figures above. Densities and bag yields vary by supplier and moisture, so every one of them is editable in the calculator.
- Bag yield
- 80 lb bag = 0.60 cu ft, 45 bags per cubic yardQuikrete Concrete Mix 1101 data sheet, verified October 2026
- Concrete weight
- 150 lb per cubic footNormal concrete runs 140 to 150 lb per cubic foot. We use 150 for weight estimates.Engineering ToolBox: Concrete properties, verified October 2026
- Extra for waste
- 10%Add 10% for spillage, over-dig and an uneven base. Bump it to 15% on a rough subgrade.
- Ready-mix order
- Rounded up to the next half yardPlants sell in half-yard increments, and a short load carries a surcharge.
- 2021 IRC footing minimum
- 16 in wide by 8 in thick, at or over the 12 in by 6 in floorThe 12 in width and 6 in thickness are the floor, not the answer: the width your wall needs comes from Table R403.1, and the depth from your frost line, which only your building department can tell you. Footings may not bear on frozen soil.2023 Oregon Residential Specialty Code, Chapter 4 (2021 IRC text, published by ICC), verified November 2026
- Depth below grade
- At least 12 in, or below the frost lineYour frost line is local and the code only names the table, so ask your building department for the figure before you dig. Footings may not bear on frozen soil.2023 Oregon Residential Specialty Code, Chapter 4 (2021 IRC text, published by ICC), verified November 2026